HV Network Reinforcement
Location
Wiltshire, UK
Client
UKPN
Main Contractor
blu-3 (UK)
Value
£500k
Challenges and Solutions:
- Third-party approvals and urgent requirements for HV supply to the site provided early complications
- By proactively engaging with local authorities, blu-3 ensured all parties were satisfied with lead times and go-live dates
- blu-3 saved the client money by devising a methodology that eliminated the need for temporary utility supplies
Scope of the project:
- Installation of HV ducting and cables
- Liaising with Brighton and Hove Albion Football Club and UKPN to avoid disruption
- Preparation for the future use of residential and commercial units