33kV Network improvement

Bulford 3rd feeder

HV Network Reinforcement

Location

Wiltshire, UK

Client

UKPN

Main Contractor

blu-3 (UK)

Value

£500k

Challenges and Solutions:

  •  Third-party approvals and urgent requirements for HV supply to the site provided early complications 
  • By proactively engaging with local authorities, blu-3 ensured all parties were satisfied with lead times and go-live dates 
  • blu-3 saved the client money by devising a methodology that eliminated the need for temporary utility supplies

Scope of the project:

  •  Installation of HV ducting and cables 
  • Liaising with Brighton and Hove Albion Football Club and UKPN to avoid disruption 
  • Preparation for the future use of residential and commercial units