The third phase of a data centre project in Clonee, Ireland. This project was secured after two successful earlier phases at the site and proved difficult due to ground and weather conditions which the blu-3 team overcame.
Location
Ireland
Client
Confidential
Main Contractor
Mace
Value
£22M
An expansive data centre campus on a 350-acre greenfield site in Clonee, Ireland.
Project Challenges & Solutions:
- Site exhibited difficult ground and weather conditions
- On site logistics with main development build
- Reactive works to support main development schedule
Scope:
- Extension of previous enabling works to support the main development of Building CLN2 including Earthworks, asphalt road construction and services
- 110,000m3 of imported stone for construction hardstandings, working platforms & storage yards
- Construction of building foundations, services & car parking for satellite office & welfare building
- Decant / demolition of all non permanent enabling works infrastructure & services