Construction and fit out including new access road construction Work Package A – Construction of a new substation compound, inclusive of a new Switchroom. Work Package B – Installation and Commissioning of Substation external and buried Earthing System.
The new Switchroom building and cable trench shall be constructed. The building and switchgear will be completed to a point where they are ready to be put into service When the bases are ready, new plant will be installed and commissioned: Transformer 1 HV cables Package Substation in GRP housing Associated LV and auxiliary cables All new plant will be energised and put into service. The existing Transformer 2 will be taken out of service and removed from site freeing the space to construct the new Transformer 2 and 3 bund and plinths, drainage, access road, cable access ways and ducting and alterations to the site fence.